Kilbourne to Poplar City 69kV Line Distribution

Client Prairie Power, Inc.
Completion Date 2020
Location Illinois
Completed by The L.E. Myers Co.

Over an existing 12kV line, L.E. Myers crews built a 69/12kV line that feeds the Kilbourne Substation. Construction included 10.5 miles of new 336 ACSR 69kV and 12kV conductor and 257 poles – 249 wood, three laminate, and three steel poles.